Moss Vale Data Centre
Mechanical Services Installation – Critical Cooling Infrastructure
Status: Completed – June 2025
Project Scope
HVAC Industries was engaged by Programmed Electrical Technologies Pty Ltd to deliver the mechanical services installation for the Moss Vale Data Centre, focusing on the installation of critical cooling infrastructure required to support the facility’s IT environments.
Data centre facilities require highly reliable mechanical systems capable of maintaining stable environmental conditions, redundancy, and continuous operational performance. HVAC Industries worked closely with the client and project stakeholders to ensure all cooling infrastructure was installed in accordance with the project specifications, commissioning procedures, and operational requirements associated with data centre environments.
The project involved the installation and commissioning of precision cooling systems, ensuring that temperature and humidity conditions within the server rooms could be maintained within strict operating tolerances.
Commissioning & Compliance
• Full system air balancing and performance testing
• System commissioning to verify compliance with design intent
• Preparation and delivery of O&M manuals
• Provision of as-built drawings and documentation
• Installation works covered by a 24-month defect liability period
All works completed in compliance with NCC requirements and AS1668 standards
Installation Standards & Quality Assurance
Exhaust ventilation systems for toilets, laundries, and kitchens across all apartments
Lobby ventilation system incorporating outside air supply with roof-mounted fans
Car park ventilation system including:
• Supply and exhaust fans
• Jet fan system
• CO sensor-controlled VSD operation
• Full compliance with AS1668 ventilation standards
Ventilation systems installed for:
• Plant rooms
• Utility rooms
• Fire pump rooms
Precision Cooling Systems
Upon completion of installation works, HVAC Industries carried out full commissioning procedures including:
• System testing and verification in accordance with ITP documentation
• Refrigerant system pressure testing and leak verification
• Performance verification of the cooling systems
• Preparation and delivery of as-built documentation and O&M manuals
• Final inspection and certification of installed systems
All works were completed in accordance with the approved design documentation and mechanical specifications for the facility.